Downtown Streetscape Update – June 23, 2015

From the office of Town Administrator Jeff Nutting, here’s the latest update on the downtown construction…

“Downtown Project Update #5
The binder course (base coat) will be put down on Summer Street on July 1 or 2 depending on the weather.

The binder course will be put down on High Street and Main Street from Pleasant to School Street during the same time period.
Main Street at Church Square, Monday, June 22.
High Street on Monday, June 22.
They will begin replacing the Emmons Street sidewalk at the end of this week or next week.
Work at the corner of Emmons and West Central Street (old municipal building) will commence next week, including the installation of the traffic light bases.
The period lighting bases installation will continue over the summer at several locations.
The sidewalk reconstruction of West Central Street will begin mid to late July.
If anyone has a question please feel free to reach out to the DPW Director, Brutus Cantoreggi or Town Engineer, Michael Maglio at 508-553-5500 or Maxine at 508-520-4949.”

– See more at: http://www.franklindowntownpartnership.org/2015/06/downtown-streetscape-project-update-5.html#sthash.INU8xu2z.dpuf

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s