From the office of Town Administrator Jeff Nutting, here’s the latest update on the downtown construction…

wip

  • “Proposed work for the weeks of September 5 and September 12
  • Mill transitions on side streets and continue to raise castings and prep for paving.
  • Pave Main Street from School Street to Pleasant Street (from the Library to St. Mary’s Church).
  • Install bollards and finish sidewalk at Dean College pedestrian crosswalk.
  • Complete boxcut and binder coat at Emmons and West Central streets.
  • Work on underground utilities for site lighting and signals at Emmons and West Central streets.
  • Begin curb installation on West Central Street on approximately September 10.
  • Begin landscaping and seeding on Lincoln and Main streets.

If anyone has a question please feel free to reach out to the DPW Director, Brutus Cantoreggi, or Town Engineer, Michael Maglio, at 508-553-5500, or Jeffrey Nutting, Town Administrator, at 508-520-4949.”

You can also learn more about the construction at the next Franklin Downtown Partnership general meeting, tomorrow morning at 8:30 AM. The meeting will be held in the Dean College Campus Center’s Golder Room.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s