Downtown Streetscape Update -April 12, 2016

From the office of Town Administrator Jeff Nutting, here’s the latest on the downtown construction…

  
“This week, expect the curbing construction to continue. Please be aware of any detours the construction crew may have up as you approach downtown. 

The week of April 18th, expect new sidewalk construction to begin. 

The following week, please expect Main Street sidewalk and curb construction to get started. There will not be any constriction crews on Monday, April 18th in observance of Patriots Day. 

The project remains on schedule to be fully completed by Labor Day at the end of the summer. Follow the Town on Facebook and Twitter for the most recent updates.”

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s